To All,
We continue to have delays on the DPO’s for this project. The Contractor just requested that I inquire about this one.
I believe Alex told me this morning that was with Contracts?
DPO’s need to be issued within 1 week of receiving.
Sincerely,
Ramon D. Gavarrete, P.E.
Public Works Director
Alachua County Public Works
5620 NW 120th Lane
Gainesville, FL 32653
Direct: (352) 548-1214
Fax: (352) 337-6243
Cell: (863) 381-6875
PLEASE NOTE: Florida has a very broad public records law (F. S. 119). All e-mails
to and from County Officials are kept as public records. Your e-mail communications, including your e-mail address, may be disclosed to the public and media at any time.
From: Laura Botero <[log in to unmask]>
Sent: Wednesday, April 3, 2024 1:39 PM
To: Public Works Fiscal <[log in to unmask]>
Cc: Ramon D. Gavarrete <[log in to unmask]>; Rafael Rincon <[log in to unmask]>; Alexandra Corales <[log in to unmask]>; Cerra B. Shires <[log in to unmask]>; Jenna Beck <[log in to unmask]>; Ryan Stroh <[log in to unmask]>
Subject: Request for DPO & DCO for Mack Concrete, AC Fire Station 21
Good morning,
Please see attached requests & paperwork for Mack Concrete - AC Fire Station 21
It's a new vendor to Scorpio. Do you know if this vendor is registered with the county already or will they need Vendor Entry form/W9/EFT form?
Thank you