Mr. Amar,
I am in receipt of your email below.
On March 8, 2024, Public Works received a request from the Contractor, VE Whitehurst, to delay the start date
on the project due to challenges with the delivery of the Drainage Structures. Each structure must be constructed as to the depths and types as per plans. The request was for the new date to be twelve (12) weeks from the approval of Shop Drawings by the
County.
The revised Notice to Proceed (NTP) for the subject project now sets the start date of June 3, 2024. It is good
construction practices to complete any asphalt work until all drainage, including culvert crossings are installed.
If you have any questions or require additional information, please feel free to contact me.
NW 23rd is in worse conditions than SW 24th. However, SW 24th also presented
deteriorating conditions. The Board has adopted a Pavement Management System with several parameters. Pavement condition is only one parameter. Other factors that are considered by the program are Traffic Volumes, Surface Conditions work orders, Areas of
Inequity, overall age of the asphalt, and a very complicated algorithm. Pavement Management is not necessarily “worse first”. The goal is to improve the roadway before the surface gets to the critical point of deterioration and therefore, avoid greater expense.
If you have any questions or require additional information, please feel free to contact me.
Sincerely,
Ramon D. Gavarrete, P.E.
Public Works Director
Alachua County Public Works
5620 NW 120th Lane
Gainesville, FL 32653
Direct: (352) 548-1214
Fax: (352) 337-6243
Cell: (863) 381-6875
PLEASE NOTE: Florida has a very broad public records law (F. S. 119). All e-mails
to and from County Officials are kept as public records. Your e-mail communications, including your e-mail address, may be disclosed to the public and media at any time.
To unsubscribe from the CHARLES-S-CHESTNUT list, click the following link:
&*TICKET_URL(CHARLES-S-CHESTNUT,SIGNOFF);